§964. Limit of time for completion of Colorado and Wyoming pipelines; forfeiture

As of today

View this section as of a date


Notable points in this section's history

Latest NOW
· Cited by 3 provisions

43 U.S.C. § 964

If any section of said pipe line shall not be completed within five years after the location of said section, the right granted in sections 962 to 965 of this title shall be forfeited, as to any incomplete section of said pipe line, to the extent that the same is not completed at the date of the forfeiture.
Notes, amendments, and revision history

(May 21, 1896, ch. 212, § 3, 29 Stat. 127.)

Statutory Notes and Related Subsidiaries

Repeal; Savings Provision

Section repealed by Pub. L. 94–579, title VII, § 706(a), Oct. 21, 1976, 90 Stat. 2793, effective on and after Oct. 21, 1976, insofar as applicable to the issuance of rights-of-way over, upon, under, and through the public lands and lands in the National Forest System. Such repeal not to be construed as terminating any valid lease, permit, patent, etc., existing on Oct. 21, 1976, see section 701 of Pub. L. 94–579, set out as a note under section 1701 of this title.