§4707. Remission of liquidated damages
As of today
View this section as of a date
Notable points in this section's history
Latest NOW As originally enacted Jan 4, 201141 U.S.C. § 4707
When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.
Notes, amendments, and revision history
(Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3799.)